# Implementation Plan - Fix Version Mismatch
## Phase 1: Fix & Process Update
## Phase 1: Fix & Process Update [checkpoint: 944ce96]
- [x] Task: Run version sync script e17bf4d
- [x] Execute `deno task sync-version` (via Docker) to automatically update `icalendar.ts`, `icalendar.plug.yaml`, and `PLUG.md` to match `deno.json`.
- [x] Task: Update Workflow Protocol 9bcfaa7
- [x] Modify `conductor/workflow.md` -> "Track Completion Protocol" -> "Version Bump" section.
- [x] Replace manual file list with instruction: "Update `deno.json` version and run `deno task sync-version`".
- [ ] Task: Conductor - User Manual Verification 'Fix & Process Update' (Protocol in workflow.md)
- [x] Task: Conductor - User Manual Verification 'Fix & Process Update' (Protocol in workflow.md)