TAGS:: [[Equinix]]
- Sales team engaged to create OPE - 8/1/23
- OPE created - 8/2/23
- Quote approved - 3/30/23
- Material allocation started - 9/12/23
- Material allocation closed - 10/9/23
- Manufacturing started - 10/10/23
- Manufacturing completed - 10/16/23
- Rack Arrived at the Integration centre on 10/24/23
- Config bundles approved - 11/6/24
- PCE build start - 1/8/24
- PCE build end - 1/30/24
- PCE arrived at Equinix - 2/1/24