TAGS:: Equinix

  • Sales team engaged to create OPE - 8/1/23
  • OPE created - 8/2/23
  • Quote approved - 3/30/23
  • Material allocation started - 9/12/23
  • Material allocation closed - 10/9/23
  • Manufacturing started - 10/10/23
  • Manufacturing completed - 10/16/23
  • Rack Arrived at the Integration centre on 10/24/23
  • Config bundles approved - 11/6/24
  • PCE build start - 1/8/24
  • PCE build end - 1/30/24
  • PCE arrived at Equinix - 2/1/24