  • For all rack shipments we need to add this text to the order
    • "Note: The tie-down kit used for shipping is to be re-used for final install."


  • TODO DC15 - Issues #equinix #DC15
    • Ticket = Energize-AC Circuit - 1-232151471649
    • Email team 2024-01-24
    • 103 - order delta hardware?
      • Cant order delta hardware yet - need to validate with #Greg/ #Cheri
      • Emailed #DaveF (create mini BOM) and Greg (gimme a decision) 2024-01-30
      • Emailed group again harrasing #GregC for approval Feb 6th, 2024
      • Emailed group again harrasing #GregC for approval Feb 7th, 2024
    • 106 - #jeffm ordered parts
    • 107 - #jeffm ordered parts

  • TODO Telco Issue #Equinix collapsed:: true SCHEDULED: Feb 9th, 2024
    • ping #scott re Telco answer 2024-01-23
    • emailed thread - "where are we" 2024-01-24 10:33AM
    • emailed thread - "where are we" 2024-01-26
      • "Re: Equinix Project - Telco - connectivity"
    • Chase #Scott / Email thread 📅 2024-01-26 2024-01-26
    • 09:51 2024-01-26
      • #JaimeBell - "We have an upcoming meeting with outside counsel and will come back to you early next week with next steps."
      • pinged Jaime for update Feb 2nd, 2024
      • Dean replied, and Andreas replied back Feb 5th, 2024
  • DONE Network Rack Shipment #TR7 #Equinix completed:: Feb 6th, 2024
  • TODO PCE for Silicon Valley #Equinix #SV11