first commit
This commit is contained in:
14
pages/PCE Order Timeline.md
Normal file
14
pages/PCE Order Timeline.md
Normal file
@@ -0,0 +1,14 @@
|
||||
TAGS:: [[Equinix]]
|
||||
|
||||
- Sales team engaged to create OPE - 8/1/23
|
||||
- OPE created - 8/2/23
|
||||
- Quote approved - 3/30/23
|
||||
- Material allocation started - 9/12/23
|
||||
- Material allocation closed - 10/9/23
|
||||
- Manufacturing started - 10/10/23
|
||||
- Manufacturing completed - 10/16/23
|
||||
- Rack Arrived at the Integration centre on 10/24/23
|
||||
- Config bundles approved - 11/6/24
|
||||
- PCE build start - 1/8/24
|
||||
- PCE build end - 1/30/24
|
||||
- PCE arrived at Equinix - 2/1/24
|
||||
Reference in New Issue
Block a user