9.5 KiB
Tasks: Fitbit/Garmin Data Sync
Input: Design documents from specs/002-fitbit-garmin-sync/
Prerequisites: plan.md (required), spec.md (required for user stories), research.md, data-model.md, contracts/
Tests: Tests are included based on the TDD principle mentioned in the constitution.
Organization: Tasks are grouped by user story to enable independent implementation and testing of each story.
Format: [ID] [P?] [Story] Description
- [P]: Can run in parallel (different files, no dependencies)
- [Story]: Which user story this task belongs to (e.g., US1, US2, US3)
- Include exact file paths in descriptions
Path Conventions
- Paths shown below assume single project - adjust based on plan.md structure
Phase 1: Setup (Shared Infrastructure)
Purpose: Project initialization and basic structure
- T001 Review
sync_app.pyinbackend/src/services/sync_app.py - T002 Review
garmin/client.pyinbackend/src/services/garmin/client.py
Phase 2: Foundational (Blocking Prerequisites)
Purpose: Core infrastructure that MUST be complete before ANY user story can be implemented
⚠️ CRITICAL: No user story work can begin until this phase is complete
- T003 Add error handling to all endpoints in
backend/src/api/ - T004 Add logging at key points in
backend/src/api/andbackend/src/services/ - T005 Add missing imports for API Token, SyncApp, GarminClient, setup_logger to
backend/src/api/sync.py - T006 Add missing imports for Response, Activity to
backend/src/api/activities.py - T007 Add missing imports for func, HealthMetric to
backend/src/api/metrics.py
Checkpoint: Foundation ready - user story implementation can now begin in parallel
Phase 3: User Story 1 - Sync Activities from Garmin (Priority: P1) 🎯 MVP
Goal: Users can trigger a synchronization of their recent activities from their Garmin account so that their fitness data is stored and available within the application.
Independent Test: Trigger a sync and verify recent activities appear in the activity list. Also, verify error message when Garmin account is not connected.
Tests for User Story 1
- T008 [US1] Write unit tests for
POST /api/sync/activitiesendpoint inbackend/tests/unit/test_api/test_sync.py - T009 [US1] Write integration tests for activity sync flow in
backend/tests/integration/test_sync_flow.py
Implementation for User Story 1
- T010 [US1] Implement activity sync logic in
backend/src/api/sync.py(replace mock response with actual sync logic) - T011 [US1] Implement
sync_activitiesmethod inbackend/src/services/sync_app.pyto useGarminClient
Checkpoint: At this point, User Story 1 should be fully functional and testable independently
Phase 4: User Story 3 - Sync Health Metrics from Garmin (Priority: P1)
Goal: Users can trigger a synchronization of their daily health metrics (like steps and HRV) from their Garmin account to track their wellness over time.
Independent Test: Trigger a metric sync and see updated data in their health dashboard or metric query views.
Tests for User Story 3
- T012 [US3] Write unit tests for
POST /api/sync/metricsendpoint inbackend/tests/unit/test_api/test_sync.py - T013 [US3] Write integration tests for health metrics sync flow in
backend/tests/integration/test_sync_flow.py
Implementation for User Story 3
- T014 [US3] Create
POST /api/sync/metricsendpoint inbackend/src/api/sync.py - T015 [US3] Implement
sync_health_metricsmethod inbackend/src/services/sync_app.pyto usegarthlibrary
Checkpoint: At this point, User Stories 1 AND 3 should both work independently
Phase 5: User Story 2 - View and Query Activities (Priority: P2)
Goal: Users can list their synced activities, filter them by criteria like activity type and date, and download the original activity file for their records.
Independent Test: Navigate to the activity list, apply filters, and attempt to download a file.
Tests for User Story 2
- T016 [US2] Write unit tests for
GET /api/activities/listendpoint inbackend/tests/unit/test_api/test_activities.py - T017 [US2] Write unit tests for
GET /api/activities/queryendpoint inbackend/tests/unit/test_api/test_activities.py - T018 [US2] Write unit tests for
GET /api/activities/download/{activity_id}endpoint inbackend/tests/unit/test_api/test_activities.py
Implementation for User Story 2
- T019 [US2] Implement
list_activitiesendpoint logic inbackend/src/api/activities.py - T020 [US2] Implement
query_activitiesendpoint logic inbackend/src/api/activities.py - T021 [US2] Implement
download_activityendpoint logic inbackend/src/api/activities.py
Checkpoint: At this point, User Stories 1, 3 and 2 should all work independently
Phase 6: User Story 4 - View and Query Health Metrics (Priority: P2)
Goal: Users can see a list of all the metric types they've synced, query their data for specific time ranges, and view a high-level summary.
Independent Test: Navigate to the metrics section, select a metric type and date range, and view the resulting data and summary.
Tests for User Story 4
- T022 [US4] Write unit tests for
GET /api/metrics/listendpoint inbackend/tests/unit/test_api/test_metrics.py - T023 [US4] Write unit tests for
GET /api/metrics/queryendpoint inbackend/tests/unit/test_api/test_metrics.py - T024 [US4] Write unit tests for
GET /api/health-data/summaryendpoint inbackend/tests/unit/test_api/test_metrics.py
Implementation for User Story 4
- T025 [US4] Implement
list_available_metricsendpoint logic inbackend/src/api/metrics.py - T026 [US4] Implement
query_metricsendpoint logic inbackend/src/api/metrics.py - T027 [US4] Implement
get_health_summaryendpoint logic inbackend/src/api/metrics.py
Checkpoint: All user stories should now be independently functional
Phase 7: Polish & Cross-Cutting Concerns
Purpose: Improvements that affect multiple user stories
- T028 Review error handling across all new endpoints in
backend/src/api/ - T029 Review logging implementation across
backend/src/api/andbackend/src/services/ - T030 Add/update documentation for new API endpoints (e.g., OpenAPI spec, inline comments) in
specs/002-fitbit-garmin-sync/contracts/api-contract.yamland relevant Python files. - T031 Run quickstart.md validation as described in
specs/002-fitbit-garmin-sync/quickstart.md
Dependencies & Execution Order
Phase Dependencies
- Setup (Phase 1): No dependencies - can start immediately
- Foundational (Phase 2): Depends on Setup completion - BLOCKS all user stories
- User Stories (Phase 3+): All depend on Foundational phase completion
- User stories can then proceed in parallel (if staffed)
- Or sequentially in priority order (P1 → P1 → P2 → P2)
- Polish (Final Phase): Depends on all desired user stories being complete
User Story Dependencies
- User Story 1 (P1): Can start after Foundational (Phase 2) - No dependencies on other stories
- User Story 3 (P1): Can start after Foundational (Phase 2) - No dependencies on other stories
- User Story 2 (P2): Can start after Foundational (Phase 2) - May integrate with US1 but should be independently testable
- User Story 4 (P2): Can start after Foundational (Phase 2) - May integrate with US1/US3/US2 but should be independently testable
Within Each User Story
- Tests MUST be written and FAIL before implementation
- Models before services (where applicable)
- Services before endpoints (where applicable)
- Core implementation before integration
- Story complete before moving to next priority
Parallel Opportunities
- All Setup tasks can run in parallel.
- All Foundational tasks can run in parallel (within Phase 2).
- Once Foundational phase completes, user stories can start in parallel by different team members.
- Tests for a user story can run in parallel.
- Implementation tasks within a user story can be identified for parallel execution where there are no dependencies.
Implementation Strategy
MVP First (User Stories 1 & 3)
- Complete Phase 1: Setup
- Complete Phase 2: Foundational (CRITICAL - blocks all stories)
- Complete Phase 3: User Story 1
- Complete Phase 4: User Story 3
- STOP and VALIDATE: Test User Stories 1 and 3 independently.
- Deploy/demo if ready
Incremental Delivery
- Complete Setup + Foundational → Foundation ready
- Add User Story 1 → Test independently → Deploy/Demo (MVP!)
- Add User Story 3 → Test independently → Deploy/Demo
- Add User Story 2 → Test independently → Deploy/Demo
- Add User Story 4 → Test independently → Deploy/Demo
- Each story adds value without breaking previous stories
Parallel Team Strategy
With multiple developers:
- Team completes Setup + Foundational together
- Once Foundational is done:
- Developer A: User Story 1
- Developer B: User Story 3
- Developer C: User Story 2
- Developer D: User Story 4
- Stories complete and integrate independently
Notes
- Tasks with file paths indicate specific files to be created or modified.
- Each user story should be independently completable and testable.
- Verify tests fail before implementing.
- Commit after each task or logical group.
- Stop at any checkpoint to validate story independently.
- Avoid: vague tasks, same file conflicts, cross-story dependencies that break independence